Photograph of forms for arch sections three and five of the Winnipeg Aqueduct near Spruce Siding, Manitoba. Photograph taken by William G. Chace, Chief Engineer of the Winnipeg Aqueduct.
Contract 65 - Mile 1.5 - View of mucking hoist hauling excavated material to dump wagon on Pacific Avenue, looking east toward Xante Street. Work progressed eastward from Alexander Avenue at Yeomans Street. Buildings of Western Packing Company Ltd. (aba
Contract 65 - Mile 1.5 - View of mucking hoist dumping excavated material into dump wagon at Sta. 81+00 on Pacific Avenue, looking east toward Xante Street. Work progressed eastward from Alexander Avenue at Yeomans Street. Buildings of Western Packing C
Contract 65 - Mile 1.5 - View of mucking hoist dumping excavated material into dump wagon at Sta. 81+00 on Pacific Avenue, looking east toward Xante Street. Work progressed eastward from Alexander Avenue at Yeomans Street. Buildings of Western Packing C
Contract 65 - Mile 3.2 - View of men mucking trench for 48 inch diameter Branch 1 aqueduct at Sta. 169+00 on Pacific Avenue, looking west between Louise Street and Main Street. Work progressed westward from the west tunnel shaft. Building of The James R
Contract 65 - Mile 3.2 - View of men mucking trench for 48 inch diameter Branch 1 aqueduct at Sta. 169+00 on Pacific Avenue. Looking west between Louise Street and Main Street. Work progressed westward from the west tunnel shaft. Buiilding of The James
Contract 65 - Mile 3.2 - View of men mucking trench for 48 inch diameter Branch 1 aqueduct at Sta. 169+00 on Pacific Avenue. Looking west between Louise Street and Main Street. Work progressed westward from the west tunnel shaft. Building of The James
Contract 65 - Mile 1.5 - View of men mucking out trench for 48 inch diameter pressure pipe approx. at Sta. 80+00 on Pacific Avenue. Work progressed eastward from Alexander Avenue at Yeomans Street.
Contract 65 - Mile 1.5 - View of hoist lowering 48 inch diameter pressure pipe into trench at Sta. 79+50 on Pacific Avenue, looking east toward Xante Street. Work progressed eastward from Alexander Avenue at Yeomans Street. Buildings of Western Packing
Contract 65 - Mile 1.5 - View of hoist lowering 48 inch diameter pressure pipe into trench at Sta. 79+50 on Pacific Avenue, looking east toward Xante Street. Mucking hoist in background. Work progressed eastward from Alexander Avenue at Yeomans Street.
Contract 65 - Mile 1.5 - View of contractor's plant at Sta. 79+00 on Pacific Avenue, looking east toward Xante Street. Work progressed eastward from Alexander Avenue at Yeomans Street. Buildings of Western Packing Company Ltd. (abatoir & pork packing) a
Photograph of Kekekoziibii (Shoal Lake 40) First Nation camp at Shoal Lake. Photograph taken from the Falcon River Diversion Dyke by William G. Chace, Chief Engineer of the Winnipeg Aqueduct.
Photograph of a test section of the Winnipeg Aqueduct at the Winnipeg Exhibition Grounds. Photograph faces west towards McPhillips Street and was taken by an unknown photographer.
Photograph of the Seine River just south of the Winnipeg Aqueduct's crossing, looking southeast towards Provencher Boulevard and the Tissot area. The St. Boniface water tower can be seen behind the buildings in the background. Photographer is unknown.
Photograph of the Seine River where the Winnipeg Aqueduct crosses, looking northeast towards the Canadian Northern Railway main line and Rue Notre Dame (at right). Photographer is unknown.
Photograph of the Seine River where the Winnipeg Aqueduct crosses, looking northeast towards the Canadian Northern Railway main line and Rue Notre Dame (at right). Photographer is unknown.