Contract 65 - Mile 1.5 - View of mucking hoist dumping excavated material into dump wagon at Sta. 81+00 on Pacific Avenue, looking east toward Xante Street. Work progressed eastward from Alexander Avenue at Yeomans Street. Buildings of Western Packing C
Contract 65 - Mile 1.5 - View of contractor's plant at Sta. 79+00 on Pacific Avenue, looking east toward Xante Street. Work progressed eastward from Alexander Avenue at Yeomans Street. Buildings of Western Packing Company Ltd. (abatoir & pork packing) a
Contract 65 - Mile 1.5 - View of hoist lowering 48 inch diameter pressure pipe into trench at Sta. 79+50 on Pacific Avenue, looking east toward Xante Street. Mucking hoist in background. Work progressed eastward from Alexander Avenue at Yeomans Street.
Contract 65 - Mile 1.5 - View of mucking hoist hauling excavated material to dump wagon on Pacific Avenue, looking east toward Xante Street. Work progressed eastward from Alexander Avenue at Yeomans Street. Buildings of Western Packing Company Ltd. (aba
Contract 65 - Mile 3.2 - View of men mucking trench for 48 inch diameter Branch 1 aqueduct at Sta. 169+00 on Pacific Avenue. Looking west between Louise Street and Main Street. Work progressed westward from the west tunnel shaft. Buiilding of The James
Contract 65 - Mile 3.2 - View of men mucking trench for 48 inch diameter Branch 1 aqueduct at Sta. 169+00 on Pacific Avenue, looking west between Louise Street and Main Street. Work progressed westward from the west tunnel shaft. Building of The James R
Contract 65 - Mile 3.2 - View of men mucking trench for 48 inch diameter Branch 1 aqueduct at Sta. 169+00 on Pacific Avenue. Looking west between Louise Street and Main Street. Work progressed westward from the west tunnel shaft. Building of The James
Photograph of dump cars filling in last gap of a cofferdam between dykes at the intake of the Winnipeg Aqueduct at Indian Bay, taken from the west dyke. Photographer is unknown.
Photograph of Greater Winnipeg Water District officials, engineers, and their families at the east end of the Winnipeg Aqueduct tunnel below the Red River linking downtown Winnipeg to St. Boniface. From left to right: Chief Engineer William G. Chace, Harriet Lily Waugh (née Logan), possibly Effie Waugh, and Division Engineer J. Armstrong. Photographer is unknown.
Photograph of a Red River trestle bridge between downtown Winnipeg and St. Boniface, looking east towards the Taché surge tower. Photographer is unknown.
Photograph of the route of the Winnipeg Aqueduct's 66 inch diameter reinforced concrete pipeline, looking southeast towards where the Canadian Northern Railway line crosses Rue St. Joseph. Photograph taken from a concrete tower near the Taché surge tower by an unknown photographer.
Photograph of the Seine River crossing of the Winnipeg Aqueduct, taken from the Canadian Northern Railway tracks north of Provencher Boulevard and looking northeast towards Rue Notre Dame. Photographer is unknown.