Winnipeg in Focus is a database for archival descriptions and digital collections at the City of Winnipeg Archives.

Affichage de 175 résultats

description archivistique
Greater Winnipeg Water District Avec objets numériques
Aperçu avant impression Hierarchy Affichage :

Test on a P.S. pipe, Transcona

Contract 55 - Canada Lock Joint Pipe, Ltd. precast pipe plant in Transcona. Hydrostatic pressure test on a "P.S." section pipe - 40 pounds pressure. Same pipe section as in image 709. P.S. section pipe was designed for railway crossings and the Seine River crossing.

Greater Winnipeg Water District

Test on a P.S. pipe, Transcona

Contract 55 - Canada Lock Joint Pipe, Ltd. precast pipe plant in Transcona. Hydrostatic pressure test on "P.S." section pipe - 40 pounds pressure. Same pipe section as in image 718. P.S. section pipe was designed for railway crossings and the Seine River crossing.

Greater Winnipeg Water District

Seine River Crossing

Contract 55 - Mile 4.4 - Seine River north of aqueduct crossing location, looking northeast toward Canadian Northern Railway main line at left and Rue Notre Dame at right (pole line).

Greater Winnipeg Water District

Seine River Crossing

Contract 55 - Mile 4.4 - Seine River at aqueduct crossing location, looking northeast toward Canadian Northern Railway main line at left and Rue Notre Dame at right (pole line).

Greater Winnipeg Water District

Seine River to South of Crossing

Contract 55 - Mile 4.4 - Seine River south of aqueduct crossing location, looking southeast toward Boulevard Provencher. City of St. Boniface water tower visible above building in center of image.

Greater Winnipeg Water District

Party in Tunnel under Red River

Contract 56 - Mile 3.5 - Red River Crossing - Chief Engineer William G. Chase, Mrs. R.D. (Harriet) Waugh, G.W.W.D. Commisioner Richard Deans Waugh, (possibly) Effie Waugh, and Division Engineer J. Armstrong at East Shaft

Greater Winnipeg Water District

Résultats 1 à 20 sur 175