Contract 20 - Test Sections of Aqueduct - External load testing. Test sections of aqueduct were constructed at the Exhibition Grounds. Looking west toward McPhillips St.
Contract 55 - Canada Lock Joint Pipe, Ltd. precast pipe plant in Transcona. Hydrostatic pressure test on "P.S." section pipe - 40 pounds pressure. Same pipe section as in image 718. P.S. section pipe was designed for railway crossings and the Seine River crossing.
Contract 55 - Canada Lock Joint Pipe, Ltd. precast pipe plant in Transcona. Hydrostatic pressure test on a "P.S." section pipe - 40 pounds pressure. Same pipe section as in image 709. P.S. section pipe was designed for railway crossings and the Seine River crossing.
Contract 65 - Mile 1.5 - View of 48 inch Branch 1 aqueduct in shored trench on Pacific Avenue, looking east toward Xante Street approximately from location of pressure manhole at Sta. 77+47. Work progressed eastward from Alexander Avenue at Yeomans Stree
Contract 65 - Mile 1.5 - View of 48 inch Branch 1 aqueduct in shored trench on Pacific Avenue, looking west toward McPhillips St (note bridge across trench) approximately from pressure manhole at Sta. 77+47. Work progressed eastward from Alexander Avenue
Contract 65 - Mile 1.5 - View of contractor's plant at Sta. 79+00 on Pacific Avenue, looking east toward Xante Street. Work progressed eastward from Alexander Avenue at Yeomans Street. Buildings of Western Packing Company Ltd. (abatoir & pork packing) a
Contract 65 - Mile 1.5 - View of hoist lowering 48 inch diameter pressure pipe into trench at Sta. 79+50 on Pacific Avenue, looking east toward Xante Street. Work progressed eastward from Alexander Avenue at Yeomans Street. Buildings of Western Packing
Contract 65 - Mile 1.5 - View of hoist lowering 48 inch diameter pressure pipe into trench at Sta. 79+50 on Pacific Avenue, looking east toward Xante Street. Mucking hoist in background. Work progressed eastward from Alexander Avenue at Yeomans Street.
Contract 65 - Mile 1.5 - View of men mucking out trench for 48 inch diameter pressure pipe approx. at Sta. 80+00 on Pacific Avenue. Work progressed eastward from Alexander Avenue at Yeomans Street.
Contract 65 - Mile 3.2 - View of men mucking trench for 48 inch diameter Branch 1 aqueduct at Sta. 169+00 on Pacific Avenue. Looking west between Louise Street and Main Street. Work progressed westward from the west tunnel shaft. Buiilding of The James
Contract 65 - Mile 3.2 - View of men mucking trench for 48 inch diameter Branch 1 aqueduct at Sta. 169+00 on Pacific Avenue. Looking west between Louise Street and Main Street. Work progressed westward from the west tunnel shaft. Building of The James
Contract 65 - Mile 3.2 - View of men mucking trench for 48 inch diameter Branch 1 aqueduct at Sta. 169+00 on Pacific Avenue, looking west between Louise Street and Main Street. Work progressed westward from the west tunnel shaft. Building of The James R
Contract 65 - Mile 1.5 - View of mucking hoist dumping excavated material into dump wagon at Sta. 81+00 on Pacific Avenue, looking east toward Xante Street. Work progressed eastward from Alexander Avenue at Yeomans Street. Buildings of Western Packing C
Contract 65 - Mile 1.5 - View of mucking hoist dumping excavated material into dump wagon at Sta. 81+00 on Pacific Avenue, looking east toward Xante Street. Work progressed eastward from Alexander Avenue at Yeomans Street. Buildings of Western Packing C
Contract 65 - Mile 1.5 - View of mucking hoist hauling excavated material to dump wagon on Pacific Avenue, looking east toward Xante Street. Work progressed eastward from Alexander Avenue at Yeomans Street. Buildings of Western Packing Company Ltd. (aba
Contract 55 - Mile 3.6 - View of route of 66 inch diameter reinforced concrete pipeline (on Rue Arnaud, Rue St. Joseph and Rue Aubert) from concreting tower of Contract 56. Canadian National Railway main line cuts through upper half of image, and Seine R