Contract 65 - Mile 1.5 - View of contractor's plant at Sta. 79+00 on Pacific Avenue, looking east toward Xante Street. Work progressed eastward from Alexander Avenue at Yeomans Street. Buildings of Western Packing Company Ltd. (abatoir & pork packing) a
Contract 65 - Mile 1.5 - View of hoist lowering 48 inch diameter pressure pipe into trench at Sta. 79+50 on Pacific Avenue, looking east toward Xante Street. Work progressed eastward from Alexander Avenue at Yeomans Street. Buildings of Western Packing
Contract 65 - Mile 1.5 - View of hoist lowering 48 inch diameter pressure pipe into trench at Sta. 79+50 on Pacific Avenue, looking east toward Xante Street. Mucking hoist in background. Work progressed eastward from Alexander Avenue at Yeomans Street.
Contract 65 - Mile 1.5 - View of men mucking out trench for 48 inch diameter pressure pipe approx. at Sta. 80+00 on Pacific Avenue. Work progressed eastward from Alexander Avenue at Yeomans Street.
Contract 65 - Mile 1.5 - View of mucking hoist hauling excavated material to dump wagon on Pacific Avenue, looking east toward Xante Street. Work progressed eastward from Alexander Avenue at Yeomans Street. Buildings of Western Packing Company Ltd. (aba
Contract 65 - Mile 1.5 - View of mucking hoist dumping excavated material into dump wagon at Sta. 81+00 on Pacific Avenue, looking east toward Xante Street. Work progressed eastward from Alexander Avenue at Yeomans Street. Buildings of Western Packing C
Contract 65 - Mile 1.5 - View of mucking hoist dumping excavated material into dump wagon at Sta. 81+00 on Pacific Avenue, looking east toward Xante Street. Work progressed eastward from Alexander Avenue at Yeomans Street. Buildings of Western Packing C
Contract 65 - Mile 3.2 - View of men mucking trench for 48 inch diameter Branch 1 aqueduct at Sta. 169+00 on Pacific Avenue, looking west between Louise Street and Main Street. Work progressed westward from the west tunnel shaft. Building of The James R
Contract 65 - Mile 3.2 - View of men mucking trench for 48 inch diameter Branch 1 aqueduct at Sta. 169+00 on Pacific Avenue. Looking west between Louise Street and Main Street. Work progressed westward from the west tunnel shaft. Building of The James
Contract 65 - Mile 3.2 - View of men mucking trench for 48 inch diameter Branch 1 aqueduct at Sta. 169+00 on Pacific Avenue. Looking west between Louise Street and Main Street. Work progressed westward from the west tunnel shaft. Buiilding of The James
Photograph of Kekekoziibii (Shoal Lake 40) First Nation camp at Shoal Lake. Photograph taken from the Falcon River Diversion Dyke by William G. Chace, Chief Engineer of the Winnipeg Aqueduct.
Photograph of workers using a scow to place material from cars onto the Falcon River Diversion Dyke at Indian Bay. Photograph taken by William G. Chace, Chief Engineer of the Winnipeg Aqueduct.
Photograph of the only station woman for the construction of the Greater Winnipeg Water District Railway holding the hand of a child in front of a shelter, possibly near Shoal Lake. Photograph taken by C.J. Bruce, one of the Division Engineers for the Winnipeg Aqueduct.
Photograph of a test section of the Winnipeg Aqueduct at the Winnipeg Exhibition Grounds. Photograph faces west towards McPhillips Street and was taken by an unknown photographer.
Photograph of an apparatus for testing the permeability of the Winnipeg Aqueduct. Concrete samples can be seen on the bottom left. Photographer is unknown.
Photograph of a dredge excavating the Falcon River Diversion Canal between Indian Bay and Snowshoe Bay, with consulting Engineer James H. Fuertes standing to the right. Photograph is looking northwest and the photographer is unknown.
Photograph of forms for arch sections three and five of the Winnipeg Aqueduct near Spruce Siding, Manitoba. Photograph taken by William G. Chace, Chief Engineer of the Winnipeg Aqueduct.